Framing wall parallel floor joists.
The blocking provides a nailing surface for walls that fall between joists and serves as an evenly spaced fastening surface for finish materials such as drywall.
If the joists run perpendicular to the wall an adjustment should not be necessary.
If the joists are parallel to the new wall adjust the layout so that the wall is directly under a joist.
Floor joists are typically 2 by 8s 2 by 10s or 2 by 12s.
Ceiling joists are usually 2 by 6s or sometimes 2 by 4s if it is an older home.
You would be able to check if this is the case in your home by going up into the attic.
These building codes set the minimum requirements for construction including requirements for framing floor joists.
In residential construction the floor sheathing is generally sufficient to support the vertical load from a non bearing partition wall that is parallel to the floor joists.
If you have 3 or 4 inch diameter pipes running through the wall make the wall from 2 x 6 inch boards.
Generally floor or ceiling joists run parallel to the rafters.
This brings it down to plane with the underside of the i s and act as a drywall backer and nailer to attach the wall.
Some newer homes have manufactured i beam shaped joists.
To solve this problem install some pieces of lumber every 16 in between the two floor joist where the wall is supposed to go as you can see in the previous picture to the left of the window then nail your top plate to these pieces.
Blocking for i joists parallel to lower walls in basement brian i the walls are parallel to the i s we nail a 2x block to the top side of the bottom web at 24 to intervals the attach a 2x4 or 6 to the blocks.
Score 1 for being load bearing.
In some circumstances the wall s top plate aligns with a parallel joist which provides an anchorage surface but still requires blocking to accommodate ceiling drywall.
It s 1 5 inches lower so you have to bump it up a bit to do the blocking correctly above the flanges.
You may need to lift insulation or plywood to see the joists.
But the bottom of the i joist isn t even with the sill plate.
Floor joists and ceiling joists serve similar purposes.
This wall is running parallel to the floor joists above see picture 4.
The wall in this case is parallel with the joists so you need blocking between the sill plate and the 1st i joist.
Bearing partitions according to section r502 4 of the 2009 edition of the international residential code joists under parallel load bearing walls must be big enough to support the weight of the load they bear.
Score 1 for being non load bearing.